Europe Cargo Handle Difficult Loading of Fully Erected Crane

9th October 2015

Europe Cargo in Belgium were established in 1992 and have a proven track record of successfully handling any type of project.

The company have recently handled the heavy lift loading of a fully erected 'Gottwald Mobile Harbour Crane' weighing 326tns and its shipping to the final destination at the Congo Terminal in Pointe Noire, Republic of the Congo.

A quick turnaround was performed with the loading taking place on day 1, the lashing & securing on day 2 and the vessel sailing on day 3.

The loading is photographed in the below gallery.